The whole industry chain of DAZHIHUI’s project will be settled in Hubei in 2022, divided into three to four years of construction, the project planned total investment of 500 million rmb ,sales amout can achieve 1.5 billion rmb, tax revenue can reach 30 million rmb, can solve 2,000 local employment problems.
In 2023, the first phase of Hubei Dazhihui Project was completed and entered into the formal production stage, with 16,000 square meters of new standardized factories equipped with 672 domestic high-end water-jet looms.
The second phase of Dazhihui will build 20,000 high-standard factory buildings, 10,000 offices and dormitory buildings. and add 3 sets of Japan pretreatment machines, 6 sets of high quality elasticizer machines, and 300 sets of international high-end water jet looms.
In Phase III, Dazhihui planned to build 60000 new high-standard workshops, to invest 200 million RMB of new advanced spinning equipments, truly form a closed-loop industrial chain from spinning elastic yarn to weaving griege and create high-end, green, intelligent textile model.